PTSC M&C and SEMCO Maritime A/S signed EPC contract for Fengmiao 2 offshore substation

Ho Chi Minh City, November 13, 2026 – PTSC Mechanical & Construction (PTSC M&C), together with its consortium partner SEMCO Maritime A/S, has signed an Engineering, Procurement and Construction (EPC) contract for the offshore substation (OSS) of the 600 MW Fengmiao 2 Offshore Wind Farm in Taiwan, developed by Copenhagen Infrastructure Partners (CIP) in cooperation with Copenhagen Offshore Partners (COP).

The signing ceremony was attended by Mr. Le Manh Cuong, President and CEO of Petrovietnam, alongside senior executives from PTSC Corporation, COP, SEMCO Maritime A/S, and PTSC M&C, marking another significant milestone in their continued cooperation in offshore wind development.

Signatories of the Fengmiao 2 Offshore Substation EPC Contract (seated, from left): Mr. Frank Holm, COO Renewables, Semco Maritime; Mr. To Ngoc Tu, Managing Director, PTSC M&C; Mr. Mark Wainwright, FM2 Project CEO; and Mr. Jesper Krarup Holst, APAC Executive Vice President and Partner, COP.

Under the contract, the Consortium will undertake the engineering, procurement, fabrication, load-out, offshore hook-up, testing, and commissioning of one offshore substation, comprising a topside, jacket, and suction bucket foundations, with a combined structural weight of approximately 6,800 tonnes.

PTSC M&C will be responsible for the detailed design of the jacket and suction bucket foundations, fabrication of all major structures, including the topside, jacket, and suction bucket foundations, structural steel procurement, load-out, and selected offshore hook-up and structural completion works. SEMCO Maritime A/S will oversee topside engineering, procurement of electrical equipment and systems, and offshore testing and commissioning activities.

Fabrication is scheduled to commence in 2028. Offshore transportation and installation, followed by hook-up, testing, and commissioning, are planned for the second half of 2029, with offshore completion targeted for November 2029.

The Fengmiao 2 contract builds on the successful partnership established through Fengmiao 1. In October 2026, the Fengmiao 1 offshore substation achieved energization two months ahead of schedule, following a successful three-month offshore campaign. The project also recorded over 2.6 million working hours without a Lost Time Injury (LTI), reflecting the Consortium's strong commitment to safety, quality, and project delivery.

Building on this proven track record, PTSC M&C and SEMCO Maritime A/S are committed to delivering Fengmiao 2 safely, on schedule, and to the highest quality standards. PTSC M&C will continue investing in its engineering capabilities, fabrication facilities, and the adoption of digitalization and automation to enhance project execution and competitiveness.

With the EPC contract signed, the Fengmiao 2 project partners mark the beginning of their next phase of cooperation.

Beyond the contract itself, Fengmiao 2 further strengthens the long-term partnership between PTSC M&C, SEMCO Maritime A/S, CIP, and COP. Built on mutual trust and proven performance, this continued cooperation provides a strong foundation for future opportunities across Asia, the UK, and Europe. The signing of Fengmiao 2 further reinforces PTSC M&C's position in the international offshore wind supply chain, demonstrating the growing capabilities of Vietnamese enterprises in delivering complex offshore energy infrastructure to international standards.

Pham Minh Chau